Download Solution PDFWhich one of the following statements is NOT correct according to Gantt chart?
This question was previously asked in
UPSC ESE (Prelims) Civil Engineering 19 Feb 2023 Official Paper
Answer (Detailed Solution Below)
Option 3 : The time and operational con- currency aspects of the schedule is missed in this chart.
Free Tests
View all Free tests >
ST 1: UPSC ESE (IES) Civil - Building Materials
6.2 K Users
20 Questions
40 Marks
24 Mins
Detailed Solution
Download Solution PDFExplanation:
Barchart or Gantt Chart:
- Bar charts were introduced by Henery Gantt around 1900 A.D., therefore they are also called Gantt charts.
- A bar chart is a graphical representation of activity v/s time. It provides a visual representation of a project's timeline, showing the start and end dates of various tasks or activities, as well as their dependencies and the overall project schedule.
- Usually horizontal axis represents the time duration and the vertical axis represents activities or jobs to be performed.
- Activities are shown with the help of a bar.
- The beginning and end of each bar show the "time of start" and "time of finish" of the activity respectively.
- Therefore the length of the bar represents the time required for the completion of that activity.
- Gantt charts can show task dependencies, indicating which tasks must be completed before others can begin.
- Illustration is given on how the activities are to be distributed over the project timeline.
Since statement (3) is incorrect about the Gantt chart. Hence option (3) is correct.
Last updated on May 28, 2025
-> UPSC ESE admit card 2025 for the prelims exam has been released.
-> The UPSC IES Prelims 2025 will be held on 8th June 2025.
-> The selection process includes a Prelims and a Mains Examination, followed by a Personality Test/Interview.
-> Candidates should attempt the UPSC IES mock tests to increase their efficiency. The UPSC IES previous year papers can be downloaded here.