The recommended range of the velocity of the drainage water in the siphon barrels in m/sec is:

This question was previously asked in
UKPSC JE Civil 8 May 2022 Official Paper-II
View all UKPSC JE Papers >
  1. 1-2
  2. 2-3
  3. 3-4
  4. None of the above

Answer (Detailed Solution Below)

Option 2 : 2-3
Free
UKPSC JE CE Full Test 1 (Paper I)
1.8 K Users
180 Questions 360 Marks 180 Mins

Detailed Solution

Download Solution PDF

Explanation:

Siphon Aqueduct;

  • A syphon aqueduct is constructed where the water surface level of the drain at high flood is higher than the canal bed.
  • The horizontal floor of the barrels is provided with slopes at its ends to join the drain bed on either side.
  • The drain water flows under pressure through the barrels which act as inverted syphons hence this cross-drainage work is known as a syphon aqueduct.
  • The velocity of drainage water in the barrels of syphon aqueduct is normally limited to 2 to 3 m/sec.

​Hence option (2) is the correct answer.

Latest UKPSC JE Updates

Last updated on Mar 26, 2025

-> UKPSC JE Notification for 2025 will be out soon!

-> The total number of vacancies along with application dates will be mentioned in the notification.

-> The exam will be conducted to recruit Junior Engineers through Uttarakhand Public Service Commission. 

-> Candidates with an engineering diploma in the concerned field are eligible. 

-> The selection process includes a written exam and document verification. Prepare for the exam with UKPSC JE Previous Year Papers.

More Cross Drainage Works Questions

Get Free Access Now
Hot Links: teen patti rules teen patti all game teen patti glory teen patti classic