Download Solution PDFThe total activity slack is equal to:
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFExplanation :
Slack time
- It is the amount of time a task can be delayed before the project finish date is delayed. Thus, the slack is the difference between event times denoting the range within which an event time can vary.
- The Earliest Expected Time (TE) is the time when an event can be expected to occur earlier.
- The Latest allowable occurrence time (TE)is the latest time by which an event must occur to keep the project on schedule (without delaying the project).
- Event slack is defined as the difference between the latest event and the earliest event times. i.e. Slack = TL - TE
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
Latest start time - earliest start time
Latest finish time -earliest finish time (EFT)
Latest allowable event occurrence time - Early finish time
Last updated on May 19, 2025
-> JKSSB Junior Engineer recruitment exam date 2025 for Civil and Electrical Engineering has been released on its official website.
-> JKSSB JE exam will be conducted on 10th August (Civil), and on 27th July 2025 (Electrical).
-> JKSSB JE recruitment 2025 notification has been released for Civil Engineering.
-> A total of 508 vacancies has been announced for JKSSB JE Civil Engineering recruitment 2025.
-> JKSSB JE Online Application form will be activated from18th May 2025 to 16th June 2025
-> Candidates who are preparing for JKSSB JE can download syllabus PDF from official website of JKSSB.
-> The candidates can check the JKSSB JE Previous Year Papers to understand the difficulty level of the exam.
-> Candidates also attempt the JKSSB JE Mock Test which gives you an experience of the actual exam.