Which of the following statements about sanitary landfilling is INCORRECT?

This question was previously asked in
SSC JE Civil 07 Jun 2024 Shift 1 Official Paper - 1
View all SSC JE CE Papers >
  1. Another name of sanitary landfilling is controlled tipping.
  2. Waste is stabilised by the aerobic process alone.
  3. Refuse is dumped into a low-lying area.
  4. ln the sanitary landfilling, filling of refuse is actually carried out by dividing the entire landfill area into smaller portions called cells.

Answer (Detailed Solution Below)

Option 2 : Waste is stabilised by the aerobic process alone.
Free
Building Materials for All AE/JE Civil Exams Mock Test
15 K Users
20 Questions 20 Marks 20 Mins

Detailed Solution

Download Solution PDF

Explanation:

Sanitary Landfilling

  • Sanitary landfilling, also known as controlled tipping, is a method of waste disposal where refuse is systematically deposited in a landfill area designed to minimize environmental impact.
  • This method involves placing waste in a controlled manner, compacting it, and covering it with soil to prevent exposure to the environment and reduce odors and pests.
  • Sanitary landfilling is divided into smaller portions called cells, each of which is filled, compacted, and covered daily or regularly.

Evaluating the Statements

Statement 1: Another name of sanitary landfilling is controlled tipping.

  • This statement is correct. Sanitary landfilling is often referred to as controlled tipping.

Statement 2: Waste is stabilized by the aerobic process alone.

  • This statement is incorrect. While initial waste decomposition may involve aerobic processes, the majority of waste stabilization in sanitary landfills occurs through anaerobic processes due to the lack of oxygen in deeper layers of the landfill.

Statement 3: Refuse is dumped into a low-lying area.

  • This statement is correct. Sanitary landfills are often located in low-lying areas to contain and manage waste more effectively.

Statement 4: In the sanitary landfilling, filling of refuse is actually carried out by dividing the entire landfill area into smaller portions called cells.

  • This statement is correct. The landfill area is divided into smaller cells for better management and operational efficiency.
Latest SSC JE CE Updates

Last updated on May 28, 2025

-> SSC JE notification 2025 for Civil Engineering will be released on June 30. 

-> Candidates can fill the SSC JE CE application from June 30 to July 21.

-> The selection process of the candidates for the SSC Junior Engineer post consists of Paper I, Paper II, Document Verification, and Medical Examination.

-> Candidates who will get selected will get a salary range between Rs. 35,400/- to Rs. 1,12,400/-.

-> Candidates must refer to the SSC JE Previous Year Papers and SSC JE Civil Mock Test, SSC JE Electrical Mock Test, and SSC JE Mechanical Mock Test to understand the type of questions coming in the examination.

-> The Staff Selection Commission conducts the SSC JE exam to recruit Junior Engineers in different disciplines under various departments of the Central Government.