Question
Download Solution PDFA and B can do a piece of work in 43 days and 3 days, respectively. The number of days [Correct to one decimal place] required to complete the work if both A and B work together is:
- 0.4
- 3.9
- 2.8
- 5.8
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
A can do the work in 43 days
B can do the work in 3 days
Formula used:
Time taken to complete work together = LCM of individual times
Calculation:
Total work = LCM of 43 and 3 = 129 (since 43 and 3 are co-prime)
Efficiency of A = 129/43 = 3
Efficiency of B = 129/3 = 43
Therefore, the number of days to complete the work = 129 / 46 = 2.80 days
∴ The number of days required to complete the work together = 2.8 days
Last updated on Feb 8, 2025
-> OSSC Excise SI PET/PMT Merit List has been released on the official website. The test was conducted on 4th and 5th February 2025.
-> OSSC Excise SI 2024 Notification has been released for 10 vacancies.
-> The selection process includes Written Examination, PMT and PET, and Certificate Verification.