Question
Download Solution PDFA and B alone can do a piece of work in 4 and 9 days, respectively. In how many days will the work be completed, if they both work on alternate days, starting with B?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
A can do a piece of work = 4 days
B can do a piece of work = 9 days
Formula used:
Total work = efficiency × time
Calculation:
Efficiency | Person | Time | Total work |
9 | A | 4 | 36 |
4 | B | 9 |
Now,
(B + A) = 4 + 9 = 13 units = 2 days
⇒ (13 × 2) = 26 units = (2 × 2) = 4 days
⇒ 30 units = 5 days
⇒ 36 units = 5 + (6/9) = 5\(2\over3\) days
∴ The correct answer is 5\(2\over3\) days.
Last updated on Jun 13, 2025
-> The SSC CGL Notification 2025 has been released on 9th June 2025 on the official website at ssc.gov.in.
-> The SSC CGL exam registration process is now open and will continue till 4th July 2025, so candidates must fill out the SSC CGL Application Form 2025 before the deadline.
-> This year, the Staff Selection Commission (SSC) has announced approximately 14,582 vacancies for various Group B and C posts across government departments.
-> The SSC CGL Tier 1 exam is scheduled to take place from 13th to 30th August 2025.
-> Aspirants should visit ssc.gov.in 2025 regularly for updates and ensure timely submission of the CGL exam form.
-> Candidates can refer to the CGL syllabus for a better understanding of the exam structure and pattern.
-> The CGL Eligibility is a bachelor’s degree in any discipline.
-> Candidates selected through the SSC CGL exam will receive an attractive salary. Learn more about the SSC CGL Salary Structure.
-> Attempt SSC CGL Free English Mock Test and SSC CGL Current Affairs Mock Test.
-> Candidates should also use the SSC CGL previous year papers for a good revision.