Question
Download Solution PDFIf 450 men can finish construction of an apartment in 20 days, then how many men are needed to complete the same work in 30 days?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
450 men can finish the construction of an apartment in 20 days.
Concept used:
Total work = Number of workers × Efficiency of each worker × Number of days required
Calculation:
Let the efficiency of each man be M.
Total work = 450 × M × 20 = 9000M
Now, the number of men required to complete the task in 30 days = 9000M ÷ (M × 30) = 300
∴ 300 men can finish the construction in 30 days.
Last updated on Jun 13, 2025
-> The SSC CGL Notification 2025 has been released on 9th June 2025 on the official website at ssc.gov.in.
-> The SSC CGL exam registration process is now open and will continue till 4th July 2025, so candidates must fill out the SSC CGL Application Form 2025 before the deadline.
-> This year, the Staff Selection Commission (SSC) has announced approximately 14,582 vacancies for various Group B and C posts across government departments.
-> The SSC CGL Tier 1 exam is scheduled to take place from 13th to 30th August 2025.
-> Aspirants should visit ssc.gov.in 2025 regularly for updates and ensure timely submission of the CGL exam form.
-> Candidates can refer to the CGL syllabus for a better understanding of the exam structure and pattern.
-> The CGL Eligibility is a bachelor’s degree in any discipline.
-> Candidates selected through the SSC CGL exam will receive an attractive salary. Learn more about the SSC CGL Salary Structure.
-> Attempt SSC CGL Free English Mock Test and SSC CGL Current Affairs Mock Test.
-> Candidates should also use the SSC CGL previous year papers for a good revision.