Manish, Nakul and Pintoo alone can complete a certain work in 21days, 28 days and 15 days, respectively. Manish and Pintoo started the work together while Nakul joined them after 5 days and worked with them till the completion of the work. For how many days did Nakul work?

This question was previously asked in
SSC CPO 2024 Official Paper-I (Held On: 28 Jun, 2024 Shift 2)
View all SSC CPO Papers >
  1. 5\(\frac{1}{2}\)
  2. 2\(\frac{6}{7}\)
  3. 2\(\frac{1}{2}\)
  4. 3\(\frac{1}{2}\)

Answer (Detailed Solution Below)

Option 2 : 2\(\frac{6}{7}\)
Free
SSC CPO : General Intelligence & Reasoning Sectional Test 1
8.5 K Users
50 Questions 50 Marks 35 Mins

Detailed Solution

Download Solution PDF

Given:

Manish alone can complete the work in 21 days.

Nakul alone can complete the work in 28 days.

Pintoo alone can complete the work in 15 days.

Manish and Pintoo started the work together.

Nakul joined them after 5 days.

Formula Used:

Work done by a person in 1 day = 1 / Total days taken by the person to complete the work

Total work = Sum of work done by all in the given days

Calculation:

Work done by Manish in 1 day = 1 / 21

Work done by Pintoo in 1 day = 1 / 15

Work done by Nakul in 1 day = 1 / 28

Work done by Manish and Pintoo together in 1 day = (1 / 21) + (1 / 15)

⇒ Work done by Manish and Pintoo together in 1 day = (15 + 21) / 315

⇒ Work done by Manish and Pintoo together in 1 day = 36 / 315 = 12 / 105 = 4 / 35

Work done by Manish and Pintoo in 5 days = 5 × (4 / 35)

⇒ Work done by Manish and Pintoo in 5 days = 20 / 35 = 4 / 7

Remaining work = 1 - 4 / 7

⇒ Remaining work = 3 / 7

Work done by Manish, Pintoo, and Nakul together in 1 day = (1 / 21) + (1 / 15) + (1 / 28)

⇒ Work done by Manish, Pintoo, and Nakul together in 1 day = (20 + 28 + 15) / 420

⇒ Work done by Manish, Pintoo, and Nakul together in 1 day = 63 / 420 = 3 / 20

Let Nakul worked for x days after joining:

Total work done in x days = x × (3 / 20)

Remaining work = 3 / 7

⇒ x × (3 / 20) = 3 / 7

⇒ x = (3 / 7) × (20 / 3)

⇒ x = 20 / 7

⇒ x = 2\(\frac{6}{7}\) days

Nakul worked for 2\(\frac{6}{7}\) days.

Latest SSC CPO Updates

Last updated on Jun 17, 2025

-> The SSC has now postponed the SSC CPO Recruitment 2025 on 16th June 2025. As per the notice, the detailed notification will be released in due course.  

-> The Application Dates will be rescheduled in the notification. 

-> The selection process for SSC CPO includes a Tier 1, Physical Standard Test (PST)/ Physical Endurance Test (PET), Tier 2, and Medical Test.

-> The salary of the candidates who will get successful selection for the CPO post will be from ₹35,400 to ₹112,400.     

-> Prepare well for the exam by solving SSC CPO Previous Year Papers. Also, attempt the SSC CPO Mock Tests

-> Attempt SSC CPO Free English Mock Tests Here!

More Work and Wages Questions

More Time and Work Questions